Y2021

Task IDTaskPriority
(for EG task)
Priority
(need contractor)
JIRAConfluence/Material
IC-001Maintain AGL Window Manager, Compositor, and Homescreen1311

IC-002Multi-seat support - Graphics



IC-003Waltham Refinements and improvements



IC-004Camera Support for AGL via PipeWire108

IC-005Instrument Cluster(Compositor and Windowmanager in privileged)
Including the drm lease work
-
--
IC-005.1Implement Container runtime, mangement(resource, lifecycle)
Working by EG members (Not require to contractor)
1_

IC-006Instrument Cluster(Fast boot)
dropped
-
--
IC-007Instrument Cluster(Sound system, sound server and Soundmanager in privileged))
Start at 2020. Now working.
53SPEC-3471
IC-008Instrument Cluster(DRM sharing - Current iGel work)
Maintenance for AGL upstream.
Add DRM lease support to AGL compositor (Ref. SPEC-3838)

21SPEC-3838
IC-008.1Improved integration of DRM lease with AGL Compositor - remove nested Wayland backends86

IC-008.2drm-lease-manager update
e.g.
- configuration (SPEC-3815 )
- multi-display on 1 connector (SPEC-3815 )
- feature update for IC use case : weston with lease-manager foucus on upstream
86

IC-008.3Multiple display configuration management in the Compositor108SPEC-3818
IC-008.4V4L2 overlay support for DRM Lease.
1

IC-009Instrument Cluster (Core system, which is minimal system for QM isolation uses LTS UCB)
Working by EG members (Not require contractor)
3_

IC-010OSS reference implementation for the RTOS combinations.
Develop this task with L.F. mentorship in our plan.
Implement RTOS with real-time function (ex. CAN communication) and inter OS communication using Bosch iccom.
Ref. gsoc_sat.pdf
Rename and upstreaming of Bosch iccom.
42

IC-011AGL IC integration (Qualified IC profile)
Adding board support
IC EG members may realize to the qualified ic profile at only one reference board. When we want to add another board, need to another work.
64

IC-012OSS assessment64
https://confluence.automotivelinux.org/display/IC/Architectural+criteria+of+the+reusing+existing+OSS
IC-013Non volatile RAM disk development.
PRAMFS was stopped maintenance. Need to same solution. In case of IVI PR, that same situations.
Non volatile RAM block device?.

1210

IC-014New IC components



IC-015

Switch Waltham to use WirePlumber for Audio/Video/Screen streaming
- This means adding a network streaming component to PipeWire to stream beyond another container inside the same OS
- Support streaming to other IVI screens, RSE, and/or IC





IC-016Cross-domain buffer sharing mechanism between IC<→IVI; IVI<→RSE



IC-017Requirment Spec for IC profile